GP2582

Location: 21st St to 27th St and Sahler St to Spencer St
Start Date: 05-09-22
End date: 07-31-23
Public Notice & Contact Info.
Description

Update 1/13/2023,

Gas main installation: 100% complete

Gas meters moved to outside: 0% complete – work to begin Spring 2023

Gas services reconnection work: 0% complete – work to begin Spring 2023

Gas main abandonment: 0% complete – work to begin Spring 2023

Restoration: 0% complete

Project status: 40% complete

All concrete has been temporarily repaired and will be replaced with permanent concrete Spring 2023.

Project will be dormant until March or April 2023.